Got a problem that I need some help with:
I have got a task (type = Fixed work) with a resouce assigned to it with
work=0 (milestone). If I change the duration of the task the work and cost of
the task will also change. Is it possible to avoid this? If I have another
"work rescourse" with work >0 assigned to the same task it works ok.
Regards
Sven