Milestones & Fixed Work

M

MrHarakiri

Hi
Got a problem that I need some help with:
I have got a task (type = Fixed work) with a resouce assigned to it with
work=0 (milestone). If I change the duration of the task the work and cost of
the task will also change. Is it possible to avoid this? If I have another
"work rescourse" with work >0 assigned to the same task it works ok.
Regards
Sven
 
B

Brian K - Project MVP

MrHarakiri said:
Hi
Got a problem that I need some help with:
I have got a task (type = Fixed work) with a resouce assigned to it with
work=0 (milestone). If I change the duration of the task the work and cost
of
the task will also change. Is it possible to avoid this? If I have
another
"work rescourse" with work >0 assigned to the same task it works ok.
Regards
Sven

If it is a milestone then you should not change the duration. Milestones
work best when they do not have any Duration or any resources assigned.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top