C
Cris
Good morning.
We are using MS Project 2002 to schedule our projects. And
we have found a very big problem...
For example:
We have a task like this:
Baseline Work: 99 h
Actual Work: 114 h
Remaining Work : 0 h
Today, we want to change the baseline, adding one hour. So
we are supposed to change the Work to 100 h, and then to
save the baseline. But if we do that, MS Project
automatically changes de Actual Work to 100 h:
Baseline Work: 100 h
Actual Work: 100 h
Remaining Work : 0 h
So we have lost 14 h!!!
Do you know the correct way to change the baseline without
loosing our Actual Work?
Thanks
We are using MS Project 2002 to schedule our projects. And
we have found a very big problem...
For example:
We have a task like this:
Baseline Work: 99 h
Actual Work: 114 h
Remaining Work : 0 h
Today, we want to change the baseline, adding one hour. So
we are supposed to change the Work to 100 h, and then to
save the baseline. But if we do that, MS Project
automatically changes de Actual Work to 100 h:
Baseline Work: 100 h
Actual Work: 100 h
Remaining Work : 0 h
So we have lost 14 h!!!
Do you know the correct way to change the baseline without
loosing our Actual Work?
Thanks