turner56
I am managing a plan with many tasks and resources. I have a few problems in
my baseline that I need to correct. Specifically I am trying to modify the
amount of baseline work for several tasks.
Is it possible to directly modify the work in the baseline? I am trying to
avoid the tedium of modifying the current work, updating the baseline, then
returning the current work to its pervious value. I would like to just change
the baseline work, while leaving the current planned work unchanged.
Any ideas or thoughts?
Thanks very much!