N
Nils214
ok, this is weird. I have two final tasks at the end of my project (I did
not create this project buy am trying to adapt it to new information). Now
when I move these two tasks to a position following all the previous task,
they cause approx 1/3rd of the other tasks to move to the same end date. I
have set some of these tasks to 'alap' and some to 'asap'. Originally the two
final tasks did follow the previous tasks, but after I changed the project
start date from mid 2005 to jan 01st 2006, they project has rescheduled and i
am faced with this latest incomprehensible problem.
Help, and asap if possible
Thanks
Nils214
not create this project buy am trying to adapt it to new information). Now
when I move these two tasks to a position following all the previous task,
they cause approx 1/3rd of the other tasks to move to the same end date. I
have set some of these tasks to 'alap' and some to 'asap'. Originally the two
final tasks did follow the previous tasks, but after I changed the project
start date from mid 2005 to jan 01st 2006, they project has rescheduled and i
am faced with this latest incomprehensible problem.
Help, and asap if possible
Thanks
Nils214