I
Ian
When I first set a new Project resource calendar (to change working days),
the Gant updated correctly. Now when I try to move a task assigned to that
resource (& the calendar still looks right) I get the 'Moving to Non-Working
Day' message. But my chosen day is a working day on the resource calendar
the Gant updated correctly. Now when I try to move a task assigned to that
resource (& the calendar still looks right) I get the 'Moving to Non-Working
Day' message. But my chosen day is a working day on the resource calendar