The project will now take a total of 8 weeks.
You will need to add the additional team meetings manually.
Project has no way to know that you will need the additional meetings.
If the project has a delay in the middle of 3 weeks, increase the lag
between two of the meetings if you will skip those three weeks.
There is an alternative using a hammock task. You will lose the detail of
Team Meeting1, 2, 3, 4. Instead, you could create a single task that says
"Team Meetings" that stretches from the "Start Work" milestone until the end
of the project milestone whenever it happens. You can create a hammock task
by reading FAQ#15. Click the link below, then click FAQ near the top and
scroll to the FAQ on Hammock Tasks.
For us, we would use the Hammock task since the detail of "Team Meeting"
does not produce much value. Of course, you may actually have other
recurring meetings that do add value such as monthly cost review, etc.
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project