J
JayPeak
I have 2 tasks that cannot happen at the same time. Task1 should happen
first, then task2... but, if task2 starts, task1 must wait until it is
finished (i.e., I want to build a fireplace hearth before the carpet goes in.
To avoid being late, I can put the carpet in and lay covers over the carpet
to install the fireplace. Can I show both can start, but are mutaully
exclusive? or do I have to update the predecessors once one of the task
begins?
first, then task2... but, if task2 starts, task1 must wait until it is
finished (i.e., I want to build a fireplace hearth before the carpet goes in.
To avoid being late, I can put the carpet in and lay covers over the carpet
to install the fireplace. Can I show both can start, but are mutaully
exclusive? or do I have to update the predecessors once one of the task
begins?