James_S
Hi,
I need to set-up group resources with a degree of inter-changeability
between them. For example: I have 6 "technicians", 2 of which are carpenters
only, 2 are electricians only, and 2 of them are multi-skilled with BOTH
carpentry and electrical skills. I need to know when I have reached /
exceeded the capacity of my technicians on a project.
Let’s suppose I want to allocate carpenters to a task, but I know I have 2+2
of them.
Can I set-up a hierarchy, so that when the project’s tasks needing carpentry
resource have consumed 2 carpenters, the system then selects my multi-skilled
workers to act as further carpenters ?
If I can’t set-up hierarchy for resource skills, do you have any clever
workarounds ?
James
I need to set-up group resources with a degree of inter-changeability
between them. For example: I have 6 "technicians", 2 of which are carpenters
only, 2 are electricians only, and 2 of them are multi-skilled with BOTH
carpentry and electrical skills. I need to know when I have reached /
exceeded the capacity of my technicians on a project.
Let’s suppose I want to allocate carpenters to a task, but I know I have 2+2
of them.
Can I set-up a hierarchy, so that when the project’s tasks needing carpentry
resource have consumed 2 carpenters, the system then selects my multi-skilled
workers to act as further carpenters ?
If I can’t set-up hierarchy for resource skills, do you have any clever
workarounds ?
James