Multiple Resource Profiles in 2000

G

greg

I read an earlier post and it pointed me to this website.

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Was this a new feature for 2003 or am i missing a step or a setting as it
does not seem to work in 2000. when i hold select and choose the resources,
it does not show a cumultive graph. any help appreciated

Thanks,

Greg
 
J

Jan De Messemaeker

As far as my memory goes, it did work in 2000.
Have you set a shape "For Selected Resources"?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question