Does anybody know if it possible to display more than one resource at a time
in the resource graph in Project 2003 ? I have 5 resources that I wish to
display at the same time in one view. I can do this by exporting to Excel,
but was wondering if it is possible to do it directly in Project ??
 
M

Mike Glen

Hi Hutch,

Welcome to the Microsoft Project newsgroup :)

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 