I have a resource with 4 people assigned to it. Work is equally shared.
Resource #2 is leaving the company on Friday and a new Resource (Resource #5)
is going to finish Resource #2's work. How do I stop resource #2 and add
resource #5 without screwing up the work duration and work % complete? I am
thinking that I can do this by going to the resource sheet, bring up the
resource information, and change the working time to non-working time for
Resource #2 after this Friday and for Resource #5 changing their working time
to non-working time for all dates prior to this Friday. Is this the best way
to solve my dilemma?
Resource #2 is leaving the company on Friday and a new Resource (Resource #5)
is going to finish Resource #2's work. How do I stop resource #2 and add
resource #5 without screwing up the work duration and work % complete? I am
thinking that I can do this by going to the resource sheet, bring up the
resource information, and change the working time to non-working time for
Resource #2 after this Friday and for Resource #5 changing their working time
to non-working time for all dates prior to this Friday. Is this the best way
to solve my dilemma?