Mhunter
I have three resources that must meet to discuss as situation. I assigned all
three resources to the one task.
However, one of the three will be absent on specific date so I updated that
resource's calendar accordingly. When Project 2002 Professional determines
the start/finish dates, it uses the day the one resource is absent. If
remove the available resources, it does not schedule on that day.
Is there a way (other that updating each resource's calendar to say they
aren't available even though two are) to tell Project that all three
resources must be present and thus, not to schedule the day the one resource
is absent?
three resources to the one task.
However, one of the three will be absent on specific date so I updated that
resource's calendar accordingly. When Project 2002 Professional determines
the start/finish dates, it uses the day the one resource is absent. If
remove the available resources, it does not schedule on that day.
Is there a way (other that updating each resource's calendar to say they
aren't available even though two are) to tell Project that all three
resources must be present and thus, not to schedule the day the one resource
is absent?