I have a project plan that is put together to logically explain the work
units that will occur in my project.

There is a need to also view this plan in sequential order for timing
purposes.

How can this be done?
 
J

John

dsm said:
I have a project plan that is put together to logically explain the work
units that will occur in my project.

There is a need to also view this plan in sequential order for timing
purposes.

How can this be done?

dsm,
Probably the easiest way is to sort on the Start date.

Hope this helps.
John
Project MVP
 
D

dsm

When I sort in that manner how do I print the schedule without showing the
high level tasks?
 
J

John

dsm said:
When I sort in that manner how do I print the schedule without showing the
high level tasks?

dsm,
By "high level tasks" I assume you mean the Summary Lines. First filter
out the Summary Lines by only showing lines where the Summary field is
equal to "no" (also remember to uncheck the box at the bottom of the
filter definition window for showing related Summary lines). Then sort
by Start Date.

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top