my task hierarchy

R

Rafael

With Project Server 2007, is it possible to show the task Hierarchy in "My
Tasks" view ?

For example if I assign the following tasks to a team member:

Project "New product"

Module1

Write design spec

Module 2

Write design spec

In project 2007, the team member only sees:

New product

Write design spec

Write design spec

In this way, we got a lot of problems...some ideas to resolve this ?
 
J

Jonathan Sofer

You can train your users to drill into the task and view the full path at
the top of the assignment details screen.

A customized option would be to create a custom local text field in Project
Pro and have a macro on the save event write the full path into the custom
text field and then make that custom text field available to the My Work's
"My Assignments" view.

Jonathan
 
R

Rafael

Hi,

First of all, thanks for helping me.

How do you use this "my tasks" daily. What`s your best practice ?

Do you have any other sugestion to view this way :

Task A
- Backup
- Documentation
Task B
- Backup
- Documentation



very thanks,

Rafael
 
A

Aric Katz = Katsoft

sorry i did not realize i will not do this again

Gary L. Chefetz said:
Aric:

This newsgroup is for peer-to-peer support. If you can help a poster with an
answer that doesn't offer to sell them something, please post your useful
answers here. Otherwise, your marketing efforts are unwelcome and considered
spam. I'm quite certain that Pnina would tell you the same.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 