No dice, it doesn't help.
On a fixed duration, with or without Effort Driven checked, i have the
same
problem:
With the duration set to .2, project automatically calculates work as .18
(1.6 total), Assignment Units as 11%.
It accepts me changing the units to 100% for all 9 people.
However, when I change the work to 2 hours for the first resource, it
gives
me an error stating: The resource is assigned outside the originial dates
for
task [Taskname]. The duration of this fixed-duration task will change to
accomodate the resource assignment.
On a fixed unit task, with or without Effort Driven checked, or on a fixed
work task i have the following:
With the duration set to .2, project automatically calculates work as .18
(1.6 total), Assignment Units as 11%.
It accepts me changing the units to 100% for all 9 people.
However, when I change the work to 2 hours for the first resource, it
automatically changes the duration to .43 days and begins calculating the
work. The work calculation is correct (i.e. changing all 9 people to 2
hours
totals to 18 hours work on the task). When it does this, the change in
duration automatically pushes the task to a second day (i.e. it spans 2
days)
Maybe this is a better explanation.
Thanks for your help,
Eric
JulieS said:
Hi Eric,
Double click on the task to show the Task Information dialog box. On the
Advanced tab, uncheck effort driven. Click OK.
Now as you assign additional resources, the work for each resource will
be
calculated based upon the task duration * unit assignment. The duration
will stay the same, the amount of work will increase for each new
resource
you assign.
Hope this helps. Let us know how you get along.
Julie
I have a project schedule that i'm beginning to assign resources to. One
of
my tasks, a meeting, requires 2 hours of effort from 9 people. Problem
is,
when i enter the amount of effort it changes the duration of the task.
How
can I prevent this? What i want is:
9 resources, each with 2 hours work
units 100%
Duration .25 days (i.e. a 2 hour meeting)
I've experimented with all 3 task types, and unfortunately they all
seem
to
change the numbers. Is there any way to overcome this?