I need to show breaks in the Gantt Chart, like multiple milestones of one
task. The chart needs to continue until my finish date, but inbetween i need
to indicate when, on which date the work is 30%, 50%... done. As well I need
to ishow with text what those breaks intend to indicate. How???
 
D

davegb

STF said:
I need to show breaks in the Gantt Chart, like multiple milestones of one
task. The chart needs to continue until my finish date, but inbetween i need
to indicate when, on which date the work is 30%, 50%... done. As well I need
to ishow with text what those breaks intend to indicate. How???

You can create milestones for each increment that you want to see on
the Gantt, then link the milestone to the task with a lead time in
percent. I.e., your first milestone would be linked to the task as
FS-70%, the next one at FS-50%, and so forth. They won't be on the same
line though.
To get them all on a summary line, click "Roll up to summary" in the
task information box on each one, then collapse the outline to just
show the summary.

Hope this helps in your world.
 