Need Weekly Task List for Each Resource in Shared Resource Pool

K

kwilliams

I have several projects using a Shared Resource Pool using Project
2000. I need to print a list for each resource showing the tasks they
are assigned for the week with their Work hours across project files.

Basically, I am looking for a list that gives the information I see
when looking at at week within the Resource Usage view of the Shared
Resource Pool project file, but it doesn't need to be broken out by
day. Any ideas would be greatly appreciated!

Karen
 
J

Jan De Messemaeker

Hi,

For starters, you can change the timescale in the view to reflect the week
as minor scale.
Filter for incomplete taks and Sort on Start date may help as well.
HTH
 