I have the following problem, which I have not been able to
solve via project help.
I have a milestone, call it MA, followed by a Task, call it
TA. TA is linked to MA with a finish to start link with a
+20 lag. I then have a second milestone, MB, which is a
delivery that needs to occur 4 days before TB can start. I
can't figure out how to link MB to task A to allow MB to
move automatically due to changes in MA.
I could achieve the same effect by making MB follow a
finish to start link from MA with a lag of +16 days. But
the problem with this is that if I want to change the lag
between MA and TA, I also then have to remeber to change
the lag from MA to MB. If I can have a link with negative
lag between TA and MA then things will work out OK.
I have tried using a start to finish link between TA and
MB, but project complained that the link would violate a
constraint, i.e. it thinks MB is constrined somehow. I have
no constraints entered.
Thanks.
I have the following problem, which I have not been able to
solve via project help.
I have a milestone, call it MA, followed by a Task, call it
TA. TA is linked to MA with a finish to start link with a
+20 lag. I then have a second milestone, MB, which is a
delivery that needs to occur 4 days before TB can start. I
can't figure out how to link MB to task A to allow MB to
move automatically due to changes in MA.
I could achieve the same effect by making MB follow a
finish to start link from MA with a lag of +16 days. But
the problem with this is that if I want to change the lag
between MA and TA, I also then have to remeber to change
the lag from MA to MB. If I can have a link with negative
lag between TA and MA then things will work out OK.
I have tried using a start to finish link between TA and
MB, but project complained that the link would violate a
constraint, i.e. it thinks MB is constrined somehow. I have
no constraints entered.
Thanks.