New Scope Question.... I have a plan that has the first baseline set. New
scope: updated dates along with a couple new tasks that need to be added =
Baseline 1. If in the new scope a couple of new tasks are added, the span
dates of the parent task do not reflect the new (ie. original span date of
parent task-- 1/01/06 to 1/15/06 added task should be 1/30/06: span dates
now should be 1/01/06 to 1/30/06, but because of the plan already being
baselined, the span date has to manually be adjusted). Since it has already
been baselined, is it common to have to manually adjust these dates?
Thanks!
New Scope Question.... I have a plan that has the first baseline set. New
scope: updated dates along with a couple new tasks that need to be added =
Baseline 1. If in the new scope a couple of new tasks are added, the span
dates of the parent task do not reflect the new (ie. original span date of
parent task-- 1/01/06 to 1/15/06 added task should be 1/30/06: span dates
now should be 1/01/06 to 1/30/06, but because of the plan already being
baselined, the span date has to manually be adjusted). Since it has already
been baselined, is it common to have to manually adjust these dates?