B
Bryan
My part time resource question on this group begins my thoughts in a related
area. How does one properly handle a new task in an existing project that
realistically won't start until say a week from now. I just know this based
on more info than MSP has. When I add the task, duration, and resoures it
just puts it at the begin date of the project. Leveling adds time based on
the resouce allocation. But I KNOW it won't start until weeks after project
is calculating. What's the preferred method of getting this to properly
reflect in the plan?
area. How does one properly handle a new task in an existing project that
realistically won't start until say a week from now. I just know this based
on more info than MSP has. When I add the task, duration, and resoures it
just puts it at the begin date of the project. Leveling adds time based on
the resouce allocation. But I KNOW it won't start until weeks after project
is calculating. What's the preferred method of getting this to properly
reflect in the plan?