K
keene
I inherited a Project file from a previous project. I have added a new task
with 4 subtasks indented below it. I have entered start and end dates for
each of the subtasks and the summary task correctly shows the begin and end
dates for the task (duration?). However, in the work column it does not show
the number of months to complete the task. Every other task (the ones that
were inherited with the original Project file) show the duration in the work
column. What do I need to do to get the duration to automatically be
calculated in the work column?
with 4 subtasks indented below it. I have entered start and end dates for
each of the subtasks and the summary task correctly shows the begin and end
dates for the task (duration?). However, in the work column it does not show
the number of months to complete the task. Every other task (the ones that
were inherited with the original Project file) show the duration in the work
column. What do I need to do to get the duration to automatically be
calculated in the work column?