M
MarcusLesser
Does anyone know if it's possible to link a task to the beginning of one task
(start to start) and the end of a different task (end to end) and allow the
duration to be worked out automatically. Using Project 2000 - when I try
this only one dependency (end to end) seems to take effect - ie the task
duration is kept constant. Is there a way I can set this up so that the
duration can change if the start date of one task or the end date of the
other changes?
(start to start) and the end of a different task (end to end) and allow the
duration to be worked out automatically. Using Project 2000 - when I try
this only one dependency (end to end) seems to take effect - ie the task
duration is kept constant. Is there a way I can set this up so that the
duration can change if the start date of one task or the end date of the
other changes?