Running P2000.
Could someone explain how Project uses the Project Start Date? I have a
fixed milestone task, yet when I change the Project Start Date, the date of
the milestone changes.
Is this expected behaviour - does Project convert a fixed task date to an
offset from the Project Start Date, and retain that offset when the Project
Start Date is changed? Seems a bit odd - if I fix a date I would expect it to
remain fixed.
This can be proved easily by creating a single task in a new project,
setting it as a milestone and then changing the Project Start Date.
The details of my situation are as follows:
Project start date: 20 May 05
Milestone Task: date 1 Nov 05. Start no earlier,fixed units,effort driven,
no calendar, mark task as milestone ticked, duration 0 days (not Estimated).
If I change the Project start date to 1 Apr 06, the milestone date changes
to 13 Sep 06. This is approximately the same offset from the Project start
date (5.5 months).
Thanks for any tips
Martin
Could someone explain how Project uses the Project Start Date? I have a
fixed milestone task, yet when I change the Project Start Date, the date of
the milestone changes.
Is this expected behaviour - does Project convert a fixed task date to an
offset from the Project Start Date, and retain that offset when the Project
Start Date is changed? Seems a bit odd - if I fix a date I would expect it to
remain fixed.
This can be proved easily by creating a single task in a new project,
setting it as a milestone and then changing the Project Start Date.
The details of my situation are as follows:
Project start date: 20 May 05
Milestone Task: date 1 Nov 05. Start no earlier,fixed units,effort driven,
no calendar, mark task as milestone ticked, duration 0 days (not Estimated).
If I change the Project start date to 1 Apr 06, the milestone date changes
to 13 Sep 06. This is approximately the same offset from the Project start
date (5.5 months).
Thanks for any tips
Martin