How do I change the pjct start date and move all tasks by that amo

K

kengrish

How do I move the start date of a project and get all the task and milestones
dates to change based on the change in the start date?
 
J

Jan De Messemaeker

Hi,

It depends.

- If no tasks have constraints, and there are no actual values, just click
Project, Project Information, and change the start date
- If there are tasks with actual work, first put these to 0%complete.
- If there are tasks with constraints, Show the analysis toolbar anb run
Adjust_dates

HTH
 