J
jonno
Not sure if this is possible in Project but have used another project
management system which could do this...
If I create a 2 task, 12 day duration project...(NOT resource driven)
Task 1 - 10 day duration - start on day 1 - floating start date
Task 2 - Milestone set at day 12 - Must finish on this date.
Scenario 1 - Day 3...
Task 1 was set to 10% complete on Day 1 and so start date is now fixed. %
complete has not changed for 2 days. I want the duration bar to be extended
in length as 90% of the task still remains.
Scenario 2 - Day 2...
If no-one enters a % complete value I want Task 1 to move along the chart to
start at day 2...and so on, until a % complete value is entered and the start
date is locked.
Scenario 3 - Day 12...
Any Tasks which have not been completed and which have been moved/extended
beyond my fixed milestone should turn red.
I'm not sure if Project can do any of this at all let alone automatically
but would be grateful if anyone can give me any help.
Many thanks in advance.
Jonno
management system which could do this...
If I create a 2 task, 12 day duration project...(NOT resource driven)
Task 1 - 10 day duration - start on day 1 - floating start date
Task 2 - Milestone set at day 12 - Must finish on this date.
Scenario 1 - Day 3...
Task 1 was set to 10% complete on Day 1 and so start date is now fixed. %
complete has not changed for 2 days. I want the duration bar to be extended
in length as 90% of the task still remains.
Scenario 2 - Day 2...
If no-one enters a % complete value I want Task 1 to move along the chart to
start at day 2...and so on, until a % complete value is entered and the start
date is locked.
Scenario 3 - Day 12...
Any Tasks which have not been completed and which have been moved/extended
beyond my fixed milestone should turn red.
I'm not sure if Project can do any of this at all let alone automatically
but would be grateful if anyone can give me any help.
Many thanks in advance.
Jonno