% of duration at current date

G

Ginger

I would like to add a column that shows the percentage of the duration at the
current date. i.e., I need my team to know where they *should* be as a
percentage to comare against where they are - assuming work is evenly
distributed over the duration.

Any help would be appreciated.
 
J

Jim Aksel

To properly status the schedule, first establish a [Status Date]under
Project/Project Information.... Verify all tasks with [Start]<[Status Date]
have a %Complete > 0. Also, for all tasks with [Finish]<[Status Date] they
should be 100%, if they are not 100% complete, extend the task to the right
of the [Status Date]. Move tasks with 0% Complete to the right of the [Status
Date]. There also can be no tasks with [Actual Start] or [Actual Finish]
greater than the [Status Date]. This is proper schedule preparation.

If you have properly costed resources assigned to your schedule, a status
date, and a baseline, then you should insert the Schedule Performance Index
[SPI] column. The [SPI] measures what you have actually accomplished divided
by what you scheduled to accomplish as your baseline -- a measure of 1.00
would be on schedule. SPI>1 ahead, SPI<1 behind. Explore Earned Value in
the help for more information. SPI is a **Monetary Based **measure of
complete. An SPI of 92% (or 0.92) means 8% behind the baseline spend plan.

Another choice, insert the [Status] column. [Status] will tell you if the
task is "complete", "future task", "late", "on schedule." Please note
[status] considers ahead of schedule to be "on schedule" and is a duration
based calculation.

A formula can be applied to calculate the %Complete where you should be as
of the status date. The formula must address times when [Status] is (1) Prior
to [Start], (2)during the duration of a task, and, (3) after [Finish]. The
following formula can be applied to a spare column such as [Text1]:

Left(str(IIf([Status Date]<[Start],"0",IIf([Status
Date]>[Finish],"1",ProjDateDiff([Start],[Status
Date])/[Duration]))*100),4)+"%"

The "4" controls the number of places displayed; change it to your liking.
This formula may be used to compare against **Duration Based ** measures of
complete such as %Complete. It could also be tweaked replacing [Status Date]
with [Current Date] and the results will be more dynamic. This is not
recommended since it creates a moving target.


--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
G

Ginger

thanks so much!

Jim Aksel said:
To properly status the schedule, first establish a [Status Date]under
Project/Project Information.... Verify all tasks with [Start]<[Status Date]
have a %Complete > 0. Also, for all tasks with [Finish]<[Status Date] they
should be 100%, if they are not 100% complete, extend the task to the right
of the [Status Date]. Move tasks with 0% Complete to the right of the [Status
Date]. There also can be no tasks with [Actual Start] or [Actual Finish]
greater than the [Status Date]. This is proper schedule preparation.

If you have properly costed resources assigned to your schedule, a status
date, and a baseline, then you should insert the Schedule Performance Index
[SPI] column. The [SPI] measures what you have actually accomplished divided
by what you scheduled to accomplish as your baseline -- a measure of 1.00
would be on schedule. SPI>1 ahead, SPI<1 behind. Explore Earned Value in
the help for more information. SPI is a **Monetary Based **measure of
complete. An SPI of 92% (or 0.92) means 8% behind the baseline spend plan.

Another choice, insert the [Status] column. [Status] will tell you if the
task is "complete", "future task", "late", "on schedule." Please note
[status] considers ahead of schedule to be "on schedule" and is a duration
based calculation.

A formula can be applied to calculate the %Complete where you should be as
of the status date. The formula must address times when [Status] is (1) Prior
to [Start], (2)during the duration of a task, and, (3) after [Finish]. The
following formula can be applied to a spare column such as [Text1]:

Left(str(IIf([Status Date]<[Start],"0",IIf([Status
Date]>[Finish],"1",ProjDateDiff([Start],[Status
Date])/[Duration]))*100),4)+"%"

The "4" controls the number of places displayed; change it to your liking.
This formula may be used to compare against **Duration Based ** measures of
complete such as %Complete. It could also be tweaked replacing [Status Date]
with [Current Date] and the results will be more dynamic. This is not
recommended since it creates a moving target.


--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project



Ginger said:
I would like to add a column that shows the percentage of the duration at the
current date. i.e., I need my team to know where they *should* be as a
percentage to comare against where they are - assuming work is evenly
distributed over the duration.

Any help would be appreciated.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top