M
martin.champoux
Hello,
My boss is asking me to evaluate the percentage of work not done during
the week for all tasks ?
Because a lot of time, people are not working of the tasks schedule and
she wants to determine the percentage of work that was scheduled but
not performed during a week.
Can I do that with MS-Project or do I have to calculate the numbers
manually with the timesheet ?
The only way that I know is to take all timesheet and compare the time
worked on the project vs. time doing others tasks and then you get the
hours not worked of the project.
Thanks in advance
Marty
My boss is asking me to evaluate the percentage of work not done during
the week for all tasks ?
Because a lot of time, people are not working of the tasks schedule and
she wants to determine the percentage of work that was scheduled but
not performed during a week.
Can I do that with MS-Project or do I have to calculate the numbers
manually with the timesheet ?
The only way that I know is to take all timesheet and compare the time
worked on the project vs. time doing others tasks and then you get the
hours not worked of the project.
Thanks in advance
Marty