BJH,
If I recall correctly, ordinal implies order but that can take different
forms. If you can give us an example of what you are trying to display,
it would be easier to help you.
By Ordinal I mean ordinal day of the project, instead of based on a calendar
date.
Task 1 has a duration of 5 days, starts on Day 0 and finishes on Day 4
Task 2 has a duration of 3 days(successor to Task 1), starts on Day 5 and
finishes on Day 7.
I believe the only way I can show this is to add a formula into 2 of the
number fields, looking to see if anyone has used another way to accomplish.
By Ordinal I mean ordinal day of the project, instead of based on a calendar
date.
Task 1 has a duration of 5 days, starts on Day 0 and finishes on Day 4
Task 2 has a duration of 3 days(successor to Task 1), starts on Day 5 and
finishes on Day 7.
I believe the only way I can show this is to add a formula into 2 of the
number fields, looking to see if anyone has used another way to accomplish.
BJH,
Well I'm glad you explained that because I had something completely
different in mind.
You do not need a formula or even a spare field. Go to Format/Timescale
and set the Bottom Tier label to be: 1, 2, 3, 4, ...(from Start). As
long as the Units for the bottom tier are in days, you will have exactly
what you want.
No I actually didn't try this, but looking at the drop down, they are all
time related, not ordinal.
I think I'll go forward with the VBA/Formulas as suggested.
Thanks for the help.
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.