Over allocation symbol

M

minubony

I have designed a project three resources are overallocated.
It shows overallocation symbol beside two resources and red for the other.
My question why it's not showing the over allocation symbol beside all of
them.
 
D

Dave

minubony said:
I have designed a project three resources are overallocated.
It shows overallocation symbol beside two resources and red for the other.
My question why it's not showing the over allocation symbol beside all of
them.

It's down to the period over which the application checks for
over-allocations.

If you look at the levelling dialogue, then you will see that the
application can be made to check on a week-by-week basis or
month-by-month and so on.

The symbol means that for a given week/month (or whatever period you
have selected), the resource is working more hours than are available.

The red highlighting without the symbol means (as Jan has pointed out)
that within the selected interval, the resource's work does not exceed
that which is possible, but that for smaller intervals, there is a
conflict (so more work is allocated than can be achieved in a week for
example, but over the month the work is achievable).

If you change the period in the dialogue I refer to above, you will see
that the symbols change.
 
J

JulieS

Try the URL below.
http://project.mvps.org/faqs.htm

Julie

B Sai Prasad said:
Dear Jan De Messemaeker,

Link [http://www.mvps.org/faqs.htm] does not work. Can you please let
us
know the right link?

Thanks in advance.

Regards
Sai [PMP]


Jan De Messemaeker said:
Hi,

You can read faq 34 (Overallocation occurring in less than one day)
in
http://www.mvps.org/faqs.htm

Greetings,


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

Jan De Messemaeker

Hi,

Sorry all,
It should have read http://www.mvps.org/project/faqs.htm

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
B Sai Prasad said:
Dear Jan De Messemaeker,

Link [http://www.mvps.org/faqs.htm] does not work. Can you please let us
know the right link?

Thanks in advance.

Regards
Sai [PMP]


Jan De Messemaeker said:
Hi,

You can read faq 34 (Overallocation occurring in less than one day) in
http://www.mvps.org/faqs.htm

Greetings,


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 