J
JJN
I have a project with a task requiring 32 man-hrs for completion. I have
assigned a resource at 400% in order to complete the task in one shift.
Project tells me that my resource is overallocated. Why does this happen if
I have the resource max units set to 800%?? Any help would be appreciated.
Thanks.
assigned a resource at 400% in order to complete the task in one shift.
Project tells me that my resource is overallocated. Why does this happen if
I have the resource max units set to 800%?? Any help would be appreciated.
Thanks.