R
Rhi
Hello,
I have a problem where my summary tasks are not calculating as I want them
to. The 1st phase of the project needs a weekly schedule of five 8-hr days,
and the 2nd needs four 10-hr days. I think I've entered this information
correctly under Change Working Time. I am wondering if the problem stems
from the Calendar options selected (Tools-Options-Calendar tab) since I need
it to calculate duration in two different ways and the Calendar tab only
allows one. According to text on the Calendar tab, times entered here are
only assigned if start/finish dates are entered and no times are specified.
I've specified all working times under Change Working Time, so I assumed the
Calendar tab times would be overridden. This must not be correct or I am
missing something else. Any ideas on how I can set up my calendar so I get
the correct durations? Thanks!
(I'm using Project '07)
I have a problem where my summary tasks are not calculating as I want them
to. The 1st phase of the project needs a weekly schedule of five 8-hr days,
and the 2nd needs four 10-hr days. I think I've entered this information
correctly under Change Working Time. I am wondering if the problem stems
from the Calendar options selected (Tools-Options-Calendar tab) since I need
it to calculate duration in two different ways and the Calendar tab only
allows one. According to text on the Calendar tab, times entered here are
only assigned if start/finish dates are entered and no times are specified.
I've specified all working times under Change Working Time, so I assumed the
Calendar tab times would be overridden. This must not be correct or I am
missing something else. Any ideas on how I can set up my calendar so I get
the correct durations? Thanks!
(I'm using Project '07)