RonT said:
Thanks for the reply.
All the task are "ASAP", not other constraints such as "must finish on".
The Slack setting for critical path on the Calculation page is at 0. I have
tried changing it earlier to no effect.
An additional problem has shown up since I posted originally: I have one
task that is not on the critical path according to the line from the
successor but the task and the line to the predecessor are red, denoting
Critical path. I have tried deleting the links and reestablishing them but
get the same results.
RonT,
It's been a while since I worked with critical paths so I have forgotten
some of the little quirks that might be causing your problem. However,
if you don't mind sending your file via e-mail (zip it first), I would
be happy to take a look at it and give you an answer. With a real file
to review it is much easier to diagnose problems. If the file has
sensitive information, I can provide you with a macro that will
de-sensitize it or you can also go to fellow MVP, Jack Dahlgren's
website at:
http://masamiki.com/project/macros.htm
His "scrub" macro is essentially the same as my de-sensitizing macro.
If you can't (or don't wish to) send your file, hopefully someone else
will read this thread and offer some suggestions.
John
Project MVP