Parallel Tasks

L

Lankai

I have two tasks that run in parallel. When one of them is done, I don't
need the other (basically like a race). How do I do that in Project?
 
J

JackD

When one is done, then you set the other to 100% complete. Project has no
facility for doing this automatically.
 
J

jbigroups

Use may be able to use Paste Link to accomplish this.

Copy the % Complete from Task A and then Paste Special - Paste Link
into the % Complete field of Task B.
 
T

Teresa

Thanks, jbigroups! This works perfectly for a similar situation where I need
multiple tasks to be marked as complete concurrently, but I only have work
being done on one. Great tip!
 