I have 10 sub-tasks that are marked 100% each. The summary task for these
sub-tasks only show 99% complete. Why would this occur?
sub-tasks only show 99% complete. Why would this occur?
atheil said:I have 10 sub-tasks that are marked 100% each. The summary task for these
sub-tasks only show 99% complete. Why would this occur?
Dale Howard said:atheil --
As one of the tasks of the summary task, do you have a milestone task that
is not marked as 100% complete? Let us know.
atheil said:Each task for the summary task is marked 100% complete. We are not using %
work complete.
atheil said:John,
I inserted the column %work complete--that for each sub-task related to this
particular summary task is marked at 100%. For the summary task %work
complete, it has calculated 98% and for %complete, it has calculated 99%. I'm
really confused now!
Thank you.
atheil said:John--I would be happy to send you the file. How do I go about doing that?
Aimee
John said:Aimee,
Just zip it and e-mail to the address I gave (not the address in my
header).
John