Percentages changing on other PCs.

H

Hytekjunky

I have a strange question for the Guru's. I emailed my schedule to a few
people. When they opened the schedule, they saw 1% more on their machines
than I have on mine. Apparently, my machine is the loner. Several others
machines have the same result. Is this a setting I have on my machine that
could be causing this?
 
M

Mike Glen

Hi Hytekjunky ,

Welcome to this Microsoft Project newsgroup :)

1% of what? I suspect a mis-match of calendars - make sure everyone has the
same as yours.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
H

Hytekjunky

Hey Mike,

This one was a "Boss" Typo. He appaerently let someone look at the schedule
and in doing so, they changed some % completes to see how it would effect the
overall percentage.... and then forgot to undo what they changed.

Gotta love Boss'. When I asked him to show me on his PC, I saw the problem
almost immediately.
 
M

Mike Glen

OK, Hytekjunky, thanks for the feedback - glad you found a solution.

Mike Glen
Project MVP



wrote:
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top