S
Space Cowboy
I am using MSP 2003 Pro and I understand the differences between % complete,
% work complete and physical % complete at least in terms of all the previous
posts. I want to use the physical % complete field to estimate task progress
at the summary level.
The issue I am having is that I can not update the summary tasks only the
(sub) tasks. Any help is certainly appreciated.
Thanks!
Andy
% work complete and physical % complete at least in terms of all the previous
posts. I want to use the physical % complete field to estimate task progress
at the summary level.
The issue I am having is that I can not update the summary tasks only the
(sub) tasks. Any help is certainly appreciated.
Thanks!
Andy