This may be an easy question...
I have a plan that has a baseline applied. I had to insert about 40
extra tasks totalling about 508hours of extra work. I have baselined
these tasks with original baseline.
Now prior to these tasks being entered in, the total physical %
complete was 25% and after the tasks were added, the total is now
18%. Is this correct. Is it just telling me, that 'yeah, prior to
these tasks added you were 25% physically complete yet now you are
only 18% based on the new tasks added.
The only reason im asking is mgtment is breathing down my neck for an
explanation as to why the physical % complete dropped 7% and thats all
i figured it was.
Many Thanks in advance.
Regards
Chris
I have a plan that has a baseline applied. I had to insert about 40
extra tasks totalling about 508hours of extra work. I have baselined
these tasks with original baseline.
Now prior to these tasks being entered in, the total physical %
complete was 25% and after the tasks were added, the total is now
18%. Is this correct. Is it just telling me, that 'yeah, prior to
these tasks added you were 25% physically complete yet now you are
only 18% based on the new tasks added.
The only reason im asking is mgtment is breathing down my neck for an
explanation as to why the physical % complete dropped 7% and thats all
i figured it was.
Many Thanks in advance.