Physical % Complete

C

chris.read-smith

I just want need to get another view on this.

I have a plan. Its been baselined and tracked against. I had to add
a further 38 tasks equalling 508 hours. I have saved these tasks to
the baseline.

Prior to entering these tasks into the system, the physical % complete
of the plan was 25%, now I have entered these tasks and saved them to
the baseline, my physical % complete is 18% complete.

I would expect % work complete to do something like this as it works
out a ratio of actual work against baseline work however, should
physical % complete do this.

Or is this correct. is it saying, well prior to you inserting those
jobs, yes, you were 25% physically complete however, after adding
those extra jobs into the plan, you are now only 18% complete.

Only asking because typical management are questioning why the
physical % complete has dropped 7%.

Many Thanks

Chris
 
J

Jim Aksel

Your total EAC went up. Physical%Complete is tracking correctly.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top