M
Mike Roosevelt
I am attempting to drive completion of a task by marking the completion of
its predecessor tasks. That is, given task A with predecessors 1-8, I would
like task A to show incremental increases in completion % whenever I check
off one of the predecessor tasks as 100% complete. Is this possible to do or
could someone help me write a macro for it?
Thanks!
Mike
its predecessor tasks. That is, given task A with predecessors 1-8, I would
like task A to show incremental increases in completion % whenever I check
off one of the predecessor tasks as 100% complete. Is this possible to do or
could someone help me write a macro for it?
Thanks!
Mike