I am working on a project with 15-20 project schedules in Standard 2003.
There are many cross project links and resources (through a global resource
pool). After 2 years, we are starting see some strange activity in the
schedules.
A project that previously had multiple tasks marked complete was opened and
those tasks are now marked incomplete. We know that they were previously
marked complete after looking at a recent (within a week) backup.
What is happening here?