S
shooter27
When I use a project schedule that has not been resource leveled and when I
go into the Resource Graph, it shows the resources that are overallocated in
certain time frames - which is as designed. I prefer not to resource level.
However, when tasks are marked as completed, they remain on the Resource
Graph. Especially for time frames when overallocation exists, it would be
great if the overallocation would disapper for those task that have allready
been completed. Is there a way for the Resource Graph to only show
incomplete tasks?
go into the Resource Graph, it shows the resources that are overallocated in
certain time frames - which is as designed. I prefer not to resource level.
However, when tasks are marked as completed, they remain on the Resource
Graph. Especially for time frames when overallocation exists, it would be
great if the overallocation would disapper for those task that have allready
been completed. Is there a way for the Resource Graph to only show
incomplete tasks?