tonym
In my project file I have a number of main tasks using the same resources.
There are 3 sub tasks to complete for each main task. These sub tasks must be
completed in order and are prioritised so that task 1 is always performed
before any task 2 or 3 and any task 2 is performed before task 3. I then want
the first task to complete task 1 to complete task 2 and task 3 first. At
initial setup this can be done but if the start dates change then the the
first task 1 is not always the first task to finish task 3.
Is it possible to make the priority setting a calculated number related some
how to the start date of the task.
There are 3 sub tasks to complete for each main task. These sub tasks must be
completed in order and are prioritised so that task 1 is always performed
before any task 2 or 3 and any task 2 is performed before task 3. I then want
the first task to complete task 1 to complete task 2 and task 3 first. At
initial setup this can be done but if the start dates change then the the
first task 1 is not always the first task to finish task 3.
Is it possible to make the priority setting a calculated number related some
how to the start date of the task.