N
NewbieCB
I am having trouble entering start and finish dates for some tasks. I would
like to be able to set my start and finish dates regardless of resoruce units
etc.. Therefore I though I could use a task type of fixed duration. I then
enter in a few tasks and it is allowing me to set my start and finish dates
as well as assign resources and units to each resource. However every few
tasks I run into a problem where I can't set the start or finish. If I choose
a date for the finish it sets the start date to the same day. If I then
change the start date it changes the finish to the same day. It is almost
like it is assuming the task is a 1 day task, even before I assign resources
to it. Any ideas on what I am doing wrong? I simply want to lay out all my
tasks and choose the start and finish dates.
Thanks,
like to be able to set my start and finish dates regardless of resoruce units
etc.. Therefore I though I could use a task type of fixed duration. I then
enter in a few tasks and it is allowing me to set my start and finish dates
as well as assign resources and units to each resource. However every few
tasks I run into a problem where I can't set the start or finish. If I choose
a date for the finish it sets the start date to the same day. If I then
change the start date it changes the finish to the same day. It is almost
like it is assuming the task is a 1 day task, even before I assign resources
to it. Any ideas on what I am doing wrong? I simply want to lay out all my
tasks and choose the start and finish dates.
Thanks,