D
Dougal
I would like to use percenatage's complete to keep my project plan up to date.
I am however having a problem doing this as follows: -
I have three tasks A, B & C with each task taking 2 hrs to complete. Task C
cannot start until B has finished and B cannot start until A has finished.
After one hour of work I update my plan. I have finished task A & B in
record time and therefore set the percentage complete for task A & B as 100%
complete with only task C remaining.
The plan now shows A & B as 100% Complete with only task C remaining.
Now for my problem......the plan still stipulates that even though I have
detailed that A & B are 100% complete (following resouce levelling and
updating the plan to reflect that 1 hr has now passed) Task C is prevented
from starting for another 3 hrs (i.e. as if I still had 50% of task A to
complete and 100% of task B to complete)?
What I would like to happen is for MS Project to recognise that A & B have
been completed in less time than was originally estimated, and therefore that
Task C can now start earlier?
If anyone can help with the above it would be very much appreciated.
Yours hopefully
Dougal
I am however having a problem doing this as follows: -
I have three tasks A, B & C with each task taking 2 hrs to complete. Task C
cannot start until B has finished and B cannot start until A has finished.
After one hour of work I update my plan. I have finished task A & B in
record time and therefore set the percentage complete for task A & B as 100%
complete with only task C remaining.
The plan now shows A & B as 100% Complete with only task C remaining.
Now for my problem......the plan still stipulates that even though I have
detailed that A & B are 100% complete (following resouce levelling and
updating the plan to reflect that 1 hr has now passed) Task C is prevented
from starting for another 3 hrs (i.e. as if I still had 50% of task A to
complete and 100% of task B to complete)?
What I would like to happen is for MS Project to recognise that A & B have
been completed in less time than was originally estimated, and therefore that
Task C can now start earlier?
If anyone can help with the above it would be very much appreciated.
Yours hopefully
Dougal