B
bgane
The method I'm trying to use is to use Work & Resources to automatically
calculate Duration. As an example, I have Type set to Fixed Work. I set the
task for 15d, and then add three full-time (8hr) resources to it, one at a
time. Project correctly calculates the duration to be 5d. However, when I
set one of those resources to 50% and another to 75%, the duraction is
changed to 10d. By my calculations, it should be 6.67d (120hrs/18hrs). Am I
missing a step here?
In the same vain, I would like to add multiple resources at one time (ex: 3
75% resources at one time), but Project appears to have issues with this. I
have found a little more success adding one resource at a time.
Any help would be greatly appreciated.
calculate Duration. As an example, I have Type set to Fixed Work. I set the
task for 15d, and then add three full-time (8hr) resources to it, one at a
time. Project correctly calculates the duration to be 5d. However, when I
set one of those resources to 50% and another to 75%, the duraction is
changed to 10d. By my calculations, it should be 6.67d (120hrs/18hrs). Am I
missing a step here?
In the same vain, I would like to add multiple resources at one time (ex: 3
75% resources at one time), but Project appears to have issues with this. I
have found a little more success adding one resource at a time.
Any help would be greatly appreciated.