A
azamora2005
Hi Friends,
I'm just facing a nightmare. I'm leading a project where i do have 10
people working for it. These 10 people are not 100% for this project,
meaning that some of them work just on Mondays, and some just on
Tuesdays and Wednesdays... and so on.
Still, many just some days in the week and not always are the same
(there is no pattern).
In Project 2003 that was quite easy to asign working time, just click
on some days and then click in "non working time" or so... but now
with Project 2007 i do not have this functionality...
am i doing someting wrong? :-(((
thanks for helping!
toto.
I'm just facing a nightmare. I'm leading a project where i do have 10
people working for it. These 10 people are not 100% for this project,
meaning that some of them work just on Mondays, and some just on
Tuesdays and Wednesdays... and so on.
Still, many just some days in the week and not always are the same
(there is no pattern).
In Project 2003 that was quite easy to asign working time, just click
on some days and then click in "non working time" or so... but now
with Project 2007 i do not have this functionality...
am i doing someting wrong? :-(((
thanks for helping!
toto.