P
Peter Rooney
I have a problem with a large plan I'm working on.
It contains task data that has been copied in from other plans and I am
finding a lot of summary times that DON'T equal the sum of the tasks that
they're supposed to be summarising - they show fractional decimal numbers
much higher than they should be - I don't have ANY fractional durations -
they are all be whole numbers of days. I read that it's something to do with
the way in which Project 98 stores data (I'm using 2000 9.0.2000.0224), and
as a lot of the data that was fed into my plan historically may have come
from Project 98 users, i suspect that this may be the cause of the problem.
I don't suppose that there's a quick and easy way to correct this, is there?
Also, is there a way to format the duration and work columns so that all
entries show the same number of decimal places?
Yours hopefully
Pete
Start
It contains task data that has been copied in from other plans and I am
finding a lot of summary times that DON'T equal the sum of the tasks that
they're supposed to be summarising - they show fractional decimal numbers
much higher than they should be - I don't have ANY fractional durations -
they are all be whole numbers of days. I read that it's something to do with
the way in which Project 98 stores data (I'm using 2000 9.0.2000.0224), and
as a lot of the data that was fed into my plan historically may have come
from Project 98 users, i suspect that this may be the cause of the problem.
I don't suppose that there's a quick and easy way to correct this, is there?
Also, is there a way to format the duration and work columns so that all
entries show the same number of decimal places?
Yours hopefully
Pete
Start