J
Jianu
Hello,
I use MS Project 2003 together with MS Project Server.
I have a task that need to be set to start in a specified day and that must
finish in the same day with another task whose duration will change
(implicitly its end day will change).
I set up for the first task a "must start on" constraint, I link it with the
second task with a "finish to finish" seting and I played a lot with Fix
work, Fix units, Effort Driven and Estimate settings, but I didn't succeed to
change the task 1's duration whenever I modified the task 2's duration.
Everytime I was asked to allow a conflict between tasks and when I did that
the start and finish dates for my first task remained unchanged.
Does anybody has an ideea what to do.
Thank you very much.
I use MS Project 2003 together with MS Project Server.
I have a task that need to be set to start in a specified day and that must
finish in the same day with another task whose duration will change
(implicitly its end day will change).
I set up for the first task a "must start on" constraint, I link it with the
second task with a "finish to finish" seting and I played a lot with Fix
work, Fix units, Effort Driven and Estimate settings, but I didn't succeed to
change the task 1's duration whenever I modified the task 2's duration.
Everytime I was asked to allow a conflict between tasks and when I did that
the start and finish dates for my first task remained unchanged.
Does anybody has an ideea what to do.
Thank you very much.