V
Vit
Hi all,
here you are my situation:
I'm managing some projects on the construction field, and I have some
tasks like: Trench, Bedding, Lay pipe, Backfill...
I have inserted a custom field that tell me the amount of meter that
every task should cover...
So, for example:
TASK DURATION METERS
Trench 5d 1000
Bedding 3d 1000
Trench1 6d 1200
Backfill 2d 200
Is possible to have on a calendar base, not only the work (number of
hours of the resources), but also the daily planned production and the
actual daily production???? (just Meter divided by duration.....)
How can I solve this problem???
Thank you so much
Cheers
Ivan
here you are my situation:
I'm managing some projects on the construction field, and I have some
tasks like: Trench, Bedding, Lay pipe, Backfill...
I have inserted a custom field that tell me the amount of meter that
every task should cover...
So, for example:
TASK DURATION METERS
Trench 5d 1000
Bedding 3d 1000
Trench1 6d 1200
Backfill 2d 200
Is possible to have on a calendar base, not only the work (number of
hours of the resources), but also the daily planned production and the
actual daily production???? (just Meter divided by duration.....)
How can I solve this problem???
Thank you so much
Cheers
Ivan