A
Andrew
Hi,
I have been searching all over the internet to see whether it is
possible to program either via a macro or VB script the duration into
MS project. For several tasks I calculate the start date through the
use of predecessors and I could also calculate the stop date using a
predecessor but MSP does not have this functionality to do both start
and stop dates.
I wanted to get around this by automatically populating the duration
with the difference between to dates. Does anyone know if this is
possible?
Many Thanks,
Andrew
I have been searching all over the internet to see whether it is
possible to program either via a macro or VB script the duration into
MS project. For several tasks I calculate the start date through the
use of predecessors and I could also calculate the stop date using a
predecessor but MSP does not have this functionality to do both start
and stop dates.
I wanted to get around this by automatically populating the duration
with the difference between to dates. Does anyone know if this is
possible?
Many Thanks,
Andrew